Progetto

Intermediate Mill Revamping

Dettagli progetto

Progetto: Intermediate Mill Foundations Revamping

Servizi: Civil Detail Design and Civil works on a fast-track revamping basis

Fornitore tecnologico: Danieli Spa

Anno: 2022

Fermata: August 2022: 12 calendar days (3 days ahead of schedule) + December 2022: 14 calendar days (2 days ahead of schedule)